Almaty International Airport formally opened its modernised domestic terminal T1 on 14 November 2026. The Ministry of Transport of Kazakhstan reported this. According to the ministry, investment in the project was about $32 million, and the terminal's stated capacity is up to 9 million passengers a year. TAV Airports is named as the airport operator. Work lasted 13 months, and the terminal kept serving passengers throughout.
According to the ministry, T1 now has a renewed check-in area of 1,700 square metres and eight gate areas. It has 23 check-in desks and three new jet bridges. Baggage conveyor length has increased from 85 to 228 metres, and three-dimensional image screening has been introduced. Engineering and fire safety systems have also been updated. These parameters come from the ministry, and there has been no independent technical verification.
The airport layout explains the significance. Since June 2024 all international flights at Almaty have used the new terminal T2, while domestic flights stayed in T1. That is why the T1 upgrade touches the main flow of Kazakh carriers: Air Astana, FlyArystan, SCAT and others operating domestic flights from Almaty. Air Astana had already moved check-in for domestic flights back to T1 from 6 November 2026, when the terminal resumed work after reconstruction. The formal opening on 14 November closes that stage.
The stated capacity of up to 9 million passengers a year applies to a single terminal, but it is important to understand how it was derived. The ministry does not disclose the calculation method, and peak hourly capacity, which matters more to airlines than an annual figure, has not been named. It determines how comfortably the terminal will handle morning and evening peaks, when several domestic flights depart almost together. Measurable results for check-in queues, baggage delivery times and aircraft turnaround on domestic routes have also not been given.
The ministry's announcement concerns terminal T1 only. Other airport modernisation projects, including the runway, taxiway, cargo apron, maintenance hangar and de-icing platform, have not been declared complete by the terminal opening. That matters in winter, when airport capacity depends on apron operations as much as buildings. We covered the sector's winter preparations in Kazakhstan in a separate report: https://www.flycentralasia.com/news/en/kazakhstan-civil-aviation-winter-readiness-deicing-runway-clearance/
What has not been disclosed: the main contractor and equipment suppliers, the financing structure, the final contract cost, the method behind the 9 million figure, peak hourly capacity and operational results. Until those appear, the stated parameters are the organisers' data, not a measured result.
Our assessment: the opening of T1 completes one of Almaty's two terminal projects and brings the domestic terminal closer to T2 in standard, but the real effect will show only in operating data: queues, baggage and aircraft turnaround. For airlines and ground handlers the key question is how the new desks, gates and jet bridges will affect schedules and servicing cost. The 9 million passenger figure remains a design number for now. This is the view of flycentralasia.