Kazakhstan and the US: direct flights by end-2027 depend on FAA Category 1, TSA reviews and Air Astana's Boeing 787 deliveries

Kazakhstan expects to open direct air service with the United States by the end of 2027. The Ministry of Transport's press service said so after a meeting between Vice Minister of Transport Talgat Lastayev and US Assistant Secretary of Transportation for Aviation and International Affairs Daniel Edwards. The meeting took place on the sidelines of ICAO's Seventh Worldwide Air Transport Conference (ATConf/7) in Montreal, and the results were reported on 19 November 2026.

According to Lastayev, the legal basis is the Open Skies agreement between the two countries, and Kazakhstan expects to complete the remaining procedures in the near future. The main condition remains Category 1 status under the US Federal Aviation Administration (FAA) assessment. Without it, the country's carriers cannot begin scheduled flights to the US. According to the ministry, US experts carried out an audit in September and presented preliminary findings, which the Kazakh side described as positive. A final decision has not been announced.

The second track concerns aviation security. On 27 October it was reported that the Civil Aviation Committee had met the US Transportation Security Administration (TSA) in Astana during ICAO Aviation Security Week. The US side set out three steps before flights can begin: a review of Air Astana's aviation security programme, a check that passenger data transmission systems are compatible with the TSA's Secure Flight programme, and an aviation security assessment of the airport before flights start. These steps must be coordinated with US Department of Transportation and FAA procedures. The parties reviewed the results of a preliminary airport survey and agreed to continue work on TSA recommendations. The airport was not named.

The third element is aircraft. According to the ministry, Air Astana expects three Boeing 787 Dreamliners in 2026–2027, and they are intended for US flights. Delivery dates have moved noticeably. In August 2025 the ministry said Boeing had postponed delivery of the first aircraft to July 2026. According to Air Astana, its first Boeing 787-9 is undergoing factory flight testing, and the entry into service of the first three aircraft is given as 2027. That is an entry-into-service date, not a delivery date, so wording differs between sources. In February 2025, during the president's visit to the US, agreements were signed with Boeing for 33 aircraft worth 15 billion dollars. No delivery schedule was given for them.

What has not been disclosed. Neither the US city nor the Kazakh airport from which a flight could start has been named. There is no date for the FAA decision on Category 1 and no detail on the preliminary audit findings. The status of Air Astana's security programme and the Secure Flight check has not been disclosed. There is no confirmed delivery date for the first Boeing 787 and no timetable for launching the route. The ministry's material also gives no information on the commercial model of the service.

Our assessment: the end-2027 goal depends on three linked tracks, and none is closed yet. FAA status, TSA reviews and aircraft deliveries run in parallel, so a delay in any of them delays the rest. The stated date should be read as a target, not a schedule. For tour operators and logistics companies the signal is useful, but it is too early to plan sales. For the region it matters that Category 1 status, if obtained, would be a starting point for other carriers of the country as well. This is our own conclusion, not an official statement. This is the view of flycentralasia.