Manas: main terminal works are complete, but fit-out and baggage system remain, while the operator announces logistics and MRO plans

The main construction works on the expansion and reconstruction of the terminal complex at Manas International Airport have been completed. This was reported by Airports of Kyrgyzstan OJSC during a press tour, the results of which local media published on 11 November 2026. The terminal area has been increased by 20,000 square metres. In June it was reported that the building's total area after expansion would be about 60,000 square metres, but the November reports do not confirm that figure.

Inside the building the work is not finished. Specialists are still fitting out the premises, installing furniture and the belts of the automated baggage sorting system, connecting equipment and integrating engineering and technological systems. The terminal's commissioning date has not been named in the published materials. That matters because the schedule has already shifted: first the reconstruction was to be completed in the first quarter of 2026, then in summer 2026, and on 14 May 2026 a new section of the terminal opened to passengers while the old building was closed for reconstruction. In July the central entrance group reopened after repairs.

Outside the terminal things look better. A new access road, a multi-level car park and an overhead pedestrian walkway linking the car park to the terminal have been built, and works on the runway, taxiways and apron have been completed. Management board chairman Manasbek Samidinov told journalists on 12 November that the five-storey covered car park for 650 vehicles will have a system that finds a space by licence plate. Full launch is expected in about a month and a half, which by our calculation is late December. Parking will be paid; tariffs have not yet been approved.

Cost is a separate topic. On 8 October the Eurasian Development Bank published an analytical brief on aviation infrastructure in Central Asia, listing 770 million dollars for two projects in Kyrgyzstan: 362 million for the new Jalal-Abad airport and 408 million for Manas's airfield infrastructure. The operator disputed that estimate. By its preliminary calculations, reconstructing Manas, including terminal works, major runway repair and modernisation of related infrastructure, will cost about 130 million dollars. The final amount, the operator said, is not yet determined because some work continues, and it promised to specify it once the work is completed. The bank's and the operator's figures may describe different scopes of work, so they cannot be compared directly.

The operator also described new directions. A bonded zone and logistics hub are planned on Manas territory: the master plan provides 100,000 square metres for class A and B warehouses, with two hangars of 20,000 square metres each in the first phase. The aim is to attract large international operators and develop combined logistics. Samidinov also spoke of a project for a 40,000-square-metre cargo terminal funded by the operator's own resources, with bonded warehouses and zones for pharmaceuticals, perishables and dangerous goods, and of interest from Chinese partners and international logistics operators. Together with investors the operator is also implementing an aircraft maintenance, repair and overhaul station. The investors have not been named, and the main customers are listed as Kyrgyz carriers, including Asman Airlines, and foreign airlines flying to the region. Size, timing and scope of work are not given.

What has not been disclosed. There is no terminal commissioning date, no figures on how airport capacity will change, and no list of MRO investors. The timing of the cargo terminal and logistics hub is also not given, nor how they relate to the overall cost estimate. The materials available to us contain no information on border booths or passport control.

Our assessment: the Manas terminal is physically almost built, but passengers will feel the effect only when the baggage system, equipment and fit-out are working, and the schedule has already moved several times. Logistics and MRO remain announced plans without investors, dates or volumes, so for airlines and cargo operators this is a reason to follow the project, not to plan routes around it. The dispute over cost estimates shows that the final figure should be expected after the works are completed. This is the view of flycentralasia.